6 July 2026
Field Operations Commence Ahead of Venus-2H Drilling
Program
Ø Field operations underway at the Venus Project in Queensland's Surat Basin
Ø Site construction progressing ahead of drilling of the Venus-2H appraisal well
Ø Drilling expected to commence in mid to late July
Ø Workover of the existing Venus-1 well underway for integrated production pilot
Ø Appraisal program advances independently certified 130PJ Contingent gas
resource
Ø Major milestone in the Venus appraisal program
Sydney, 6 July 2026: Australian natural gas developer and explorer Eastern Gas Corporation Limited
(ASX: EGA) advises that the commencement of field operations at its 100%-owned Venus Project (ATP
2051) in Queensland's Surat Basin, marking the Company's first operational campaign since its
successful ASX listing earlier this year.
The mobilisation represents a significant milestone for Eastern Gas as it advances the appraisal of its
independently certified 130-petajoule¹ contingent gas resource and progresses towards potential
reserve conversion and future commercial development.
Construction of the drilling pad has commenced in preparation for drilling the Venus-2H horizontal
appraisal well, while workover operations on the existing Venus-1 well are scheduled to begin on 8 July
2026. Once completed, Venus-1 will serve as the production and monitoring well for the Company's
integrated appraisal program.
The appraisal campaign has been designed to obtain the technical data required to evaluate reservoir
performance and production characteristics across the Walloon Coal Measures. The program is
expected to generate critical information on gas deliverability, reservoir pressure behaviour, water
production and depletion performance, providing an important technical foundation for future reserve
certification and field development planning.
Venus-2H has been specifically designed as a horizontal coal seam gas appraisal well targeting the
Walloon Coal Measures. Following drilling, the well will intersect the existing Venus-1 well to establish
an integrated production pilot. This dual-well configuration is expected to deliver substantially greater
technical insight than a conventional single-well appraisal by enabling assessment of horizontal well
productivity, reservoir connectivity and sustained production performance under representative
operating conditions.
1
Refer to the geological information in Appendix B.
EasternGas.com.au | 119 Willoughby Road Crows Nest NSW 2067
EASTERN GAS CORPORATION LIMITED
ABN 71 692 331 838
Drilling of Venus-2H is scheduled to commence on 21 July 2026 and is expected to take approximately
14 days, after which the integrated production pilot will transition to flow testing and data acquisition.
The results of the appraisal program are expected to materially enhance the Company's understanding
of the Venus reservoir and support the next stage of project evaluation as Eastern Gas advances the
asset towards commercial development.
SWS workover rig to be used on Venus-1
The appraisal program has been designed to:
• assess reservoir permeability and connectivity;
• evaluate water production performance;
• monitor pressure depletion;
• assess gas deliverability;
• provide data to support future reserve conversion;
• optimise future field development planning.
The program represents another important milestone in evaluating the commercial potential of the
Venus Project's independently certified 130-petajoule1
contingent gas resource and progressing the
asset towards future development.
Management commentary
Eastern Gas Managing Director David Spring said the commencement of field operations marked a
defining milestone for the Company.
EasternGas.com.au | 119 Willoughby Road Crows Nest NSW 2067
EASTERN GAS CORPORATION LIMITED
ABN 71 692 331 838
"Commencement of field operations is an important operational milestone for Eastern Gas and follows
the completion of planning, permitting and contracting activities for the Venus appraisal program.
"While the drilling rig understandably attracts much of the attention, the work now underway is what
underpins a successful appraisal program. Preparing Venus-1 and constructing the drilling site are
critical steps that will allow us to maximise the technical information gathered once drilling begins.
"By integrating Venus-1 and Venus-2H into a single production pilot, we expect to gain a far more
comprehensive understanding of reservoir performance and gas deliverability than would be possible
through a conventional single-well appraisal.
"The integrated appraisal program has been designed to obtain technical information on reservoir
performance, pressure depletion and gas deliverability that will assist the Company in evaluating future
development options."
The commencement of field operations comes as governments, regulators and industry continue to
warn that declining production from mature gas fields will require significant new domestic supply if
future east coast energy demand is to be met.
Positioned within Queensland's prolific Surat Basin and close to established energy infrastructure, the
Venus Project is strategically located to contribute to Australia's future domestic gas requirements
should appraisal outcomes support commercial development.
Eastern Gas will continue updating shareholders and the market as drilling progresses and key
operational milestones are achieved.
This ASX Announcement has been authorised for release by the Board.
For further information, please contact:
David Spring
Managing Director
Email: investor@easterngas.com.au
EasternGas.com.au | 119 Willoughby Road Crows Nest NSW 2067
EASTERN GAS CORPORATION LIMITED
ABN 71 692 331 838
Appendix A
EasternGas.com.au | 119 Willoughby Road Crows Nest NSW 2067
EASTERN GAS CORPORATION LIMITED
ABN 71 692 331 838
Project Venus (ATP 2051) – Surat Basin
About Eastern Gas Corporation Limited
Eastern Gas Corporation Limited (ASX: EGA) is an Australian natural gas exploration and
development company focused on supplying reliable energy to east coast domestic markets.
The Company’s east coast natural gas portfolio features two highly prospective tenements in
Queensland’s prolific Surat Basin (Walloon CSG fairway) and Cooper Basin.
With a natural gas shortage and energy crisis around the world, we believe LNG will play a critical role
in fuelling the transition to a carbon-free economy in the long term. Eastern Gas is focused on
progressing its gas resources toward commercialisation to support Australia’s energy security.
Website: www.easterngas.com.au
EasternGas.com.au | 119 Willoughby Road Crows Nest NSW 2067
EASTERN GAS CORPORATION LIMITED
ABN 71 692 331 838
Appendix B
Geological Information
The geological information in this announcement relating to geological information and resources is
based on information compiled by Mr Spring, who is a Member of the Society of Petroleum Engineers
and has sufficient experience to qualify as a Competent Person. Mr Spring consents to the inclusion
of the matters based on his information in the form and context in which they appear. The information
related to the results of drilled petroleum wells has been sourced from the publicly available well
completion reports. The Company has used a conversion factor of 1.05 to convert Bcf amounts to
PJs equivalent. As reported in the Company’s Prospectus and Replacement Prospectus dated 5
December 2025 and 12 December 2025, the Project Venus contingent gas resources estimates are
1C 87.7 PJ, 2C 130.3 PJ and 3C 157.9 PJ with remaining prospective gas resources of 536 PJ (best-
case estimate). The Company confirms that it is not aware of any new information or data that
materially affects the information included in that announcement and that all material assumptions
and technical parameters underpinning the estimate continue to apply and have not materially
changed.
Cautionary Statement
The estimated quantities of petroleum that may potentially be recovered by the application of a future
development project(s) relate to undiscovered accumulations. These estimates have both a risk of
discovery and a risk of development. Further exploration appraisal and evaluation is required to
determine the existence of a significant quantity of potentially recoverable hydrocarbons.
Forward-Looking Statements
This announcement contains forward-looking statements. Forward-looking statements are not
historical facts and may be identified by the use of terminology such as “may”, “will”, “expect”,
“intend”, “plan”, “estimate”, “anticipate”, “continue”, “outlook”, “guidance” and other similar
expressions.
These forward-looking statements include, but are not limited to, statements regarding the plans,
strategies and objectives of management, anticipated production or construction commencement
dates, expected costs, resources and reserves, exploration results, production outputs and other
statements regarding future events or performance.
Forward-looking statements are based on Eastern Gas’ current expectations, estimates and
assumptions and are subject to known and unknown risks, uncertainties and other factors that may
cause actual results, performance or achievements to differ materially from those expressed or
implied in such statements. These risks include, without limitation, commodity price fluctuations,
demand variability, currency movements, drilling and production outcomes, resource and reserve
estimation risk, competition, environmental and operational risks, legislative, fiscal and regulatory
changes, economic and financial market conditions, political risk, project timing variations, approvals
and cost variations.
No assurance can be given that the forward-looking statements will prove to be correct. Readers
EasternGas.com.au | 119 Willoughby Road Crows Nest NSW 2067
EASTERN GAS CORPORATION LIMITED
ABN 71 692 331 838
should not place undue reliance on forward-looking statements.
Disclaimer
To the maximum extent permitted by law, Eastern Gas and its respective related bodies corporate,
affiliates, directors, officers, employees, agents and advisers make no representation or warranty,
express or implied, as to the accuracy, reliability, completeness or fairness of the information
contained in this announcement, nor do they accept any responsibility or liability for any loss or
damage arising from reliance on this information.
The information in this announcement is provided as at the date of this document. Except as required
by law or applicable regulation (including the ASX Listing Rules), Eastern Gas undertakes no
obligation to update or revise any forward-looking statements or other information contained in this
announcement, whether as a result of new information, future events or otherwise.
Share your feedback
Discover